Liberty Way Expansion Announced
The Veridea Group recently announced the expansion of its new Liberty Way development to include two additional acres and 24,000 square feet of office space. View the complete details in the Liberty Way Expansion Press Release. For more information regarding the Liberty Way development, view: The official Press Release The Liberty Way Fact Sheet The Veridea Group’s Liberty […]
Interior Work Continues in mBank Building
The interior of the mBank Building is nearing completion, with mBank’s December move-in date rapidly approaching. Flooring has been laid throughout the first and second floors, and furnishings and fixtures will start to arrive the week of Thanksgiving. The third floor isn’t far behind, with tenants scheduled to move in around the first of the […]
mBank Building Visually Anchors Washington & Lincoln

Rapid progress continues to be made at the developing mBank Building. Drywall is being hung throughout the basement, first and second floors along with window frames being put into place. The elevator has been delivered and will be installed in the coming week, and crews will soon start work on gutters, curbs, and light poles. […]
Exterior Work Commences On mBank Building
Crews are starting the exterior brick on the elevator and stairwell shafts this week along with setting the structural iron on the drive-thru. In addition, the electricians have begun installing transformers in the basement. For more information regarding the Liberty Way development, view: The official Press Release The Liberty Way Fact Sheet A live camera to see construction progress […]
Phase One Structural Supports Near Completion

This week, crews: Set the structural steel over the drive-thru Put up exterior metal studs on the north wall and west turret, which are what the masonry will eventually fasten to Laid block in elevator stairwell shaft on each end Next week, crews will start pouring floor slabs in the interior of the building. For […]
mBank Building Foundation Complete

On Friday, crews finished setting the last of the structural roof steel and bar joists. Feeling ambitious, they also finished pouring the last of the building’s foundation! Today, they will install the exterior metal studs that will eventually support the masonry. For more information regarding the Liberty Way development, view: The official Press Release The Liberty […]
Liberty Way Groundbreaking Ceremony
The Veridea Group announced “Liberty Way” and development plans at a Groundbreaking Ceremony held June 4, 2013. View the complete details in the Liberty Way Press Release and Fact Sheet. Pictured in photo from left to right: Patrick Gallagher, Kraus-Anderson Construction Company Jennifer Tucker, Michigan Economic Development Corporation John DePetro, Mayor of Marquette Dennis Stachewicz, City of Marquette […]
Supports for Underground Parking Ramp Under Way
Crews are continuing to build the retaining wall that will support the underground parking ramp of The Veridea Group’s 150,000 square foot mixed-use complex. The footings for the south wall and tunnel wall of the Phase I building have been completed, and progress is being made on the east and north walls! Construction began in […]
Phase One Progress
The footings for the south wall and tunnel wall of the Phase I building have been completed, and crews have moved on to the east and north walls. Construction began in April and phase I, a 28,000 square foot office building, will be completed by the late fall of this year. In addition, the first […]
Development of Phase One
Crews are now working on a retaining wall that will provide support to the ramp of the underground parking structure. Construction began in April and phase I, a 28,000 square foot office building, will be completed by the late fall of this year. In addition, the first deck of the underground parking will be completed […]